Contract package
Basalt, earthworks and irrigation-lines package
- Package value
- 8,969,556.10 SAR
- Contract period
- 2023-12-20 - 2025-06-19
- Status
- Completed

Project
RTC is delivering works at Al-Ghuroob Park in Madinah as subcontractor to Madinah Region Municipality through three separate contract packages covering basalt and earthworks with irrigation lines, the sewage network, and planting and irrigation.
Project Facts
Project
The project is delivered through three separate contract packages, each with its own scope, value, period and status. The basalt, earthworks and irrigation-lines package is complete, as is the sewage-network package, while the planting and irrigation package remains ongoing. RTC is carrying out these works at Al-Ghuroob Park in Madinah as subcontractor to Madinah Region Municipality. Package facts are presented independently below without combining values or periods into a single project total.
The packages cover basalt, cut-and-fill and irrigation lines; the sewage network; and planting and irrigation works.
The work was delivered under separate contracts. Each contract remains distinct, with its own value, period and status.
Contract package
Contract package
Contract package
Construction Delivery
Selected views of earthworks, route formation, the irrigation network and planting works.



Shows the full-site spatial arrangement and the relationship between its principal zones.